EPQ ENTRY 26: Adjusted Plan Timings

  • Robyn Salt
  • Sep 15, 2015
  • 1 min read

WEEK 14

ADJUSTED FUTURE PLAN:

OLD TIMINGS NEW TIMINGS

PHASE 3

START TARGET: WEEK 12 31/08/2015

END TARGET: WEEK 14 14/09/2015

DURATION TARGET: 2 WEEKS

PHASE 4

START TARGET: WEEK 15 21/09/2015

END TARGET: WEEK 19 19/10/2015

DURATION TARGET: 5 WEEKS

PHASE 5

START TARGET: WEEK 22 09/11/2015

END TARGET: WEEK 26 07/12/2015

DURATION TARGET: 5 WEEKS

NEW TIMINGS

SKETCHBOOK REMAKING

START TARGET: WEEK 14 16/09/2015

END TARGET: WEEK 19 19/10/2015

DURATION TARGET: 6 WEEKS

PHASE 4

START TARGET: WEEK 19 19/10/2015

END TARGET: WEEK 24 16/11/2015

DURATION TARGET: 4 WEEKS

PHASE 5

START TARGET: WEEK 24 16/11/2015

END TARGET: WEEK 28 14/12/2015

DURATION TARGET: 5 WEEKS

I have altered my plan by adding a six week period beginning this week, for me to catch up with my sketchbook. I added the buffer weeks together and cut the construction phase by a week which allows me to comfortably restore past work. However, this put more pressure on me fulfilling the strict deadlines and although I will finish before the Christmas break, I may not finish before the 11/12/2015 which was the deadline set for our project. I have written an email stating this to my tutor explaining the situation and have asked for a week deadline extension.

 
 
 