EPQ ENTRY 26: Adjusted Plan Timings
- Robyn Salt
- Sep 15, 2015
- 1 min read

WEEK 14
ADJUSTED FUTURE PLAN:
OLD TIMINGS NEW TIMINGS
PHASE 3
START TARGET: WEEK 12 31/08/2015
END TARGET: WEEK 14 14/09/2015
DURATION TARGET: 2 WEEKS
PHASE 4
START TARGET: WEEK 15 21/09/2015
END TARGET: WEEK 19 19/10/2015
DURATION TARGET: 5 WEEKS
PHASE 5
START TARGET: WEEK 22 09/11/2015
END TARGET: WEEK 26 07/12/2015
DURATION TARGET: 5 WEEKS
NEW TIMINGS
SKETCHBOOK REMAKING
START TARGET: WEEK 14 16/09/2015
END TARGET: WEEK 19 19/10/2015
DURATION TARGET: 6 WEEKS
PHASE 4
START TARGET: WEEK 19 19/10/2015
END TARGET: WEEK 24 16/11/2015
DURATION TARGET: 4 WEEKS
PHASE 5
START TARGET: WEEK 24 16/11/2015
END TARGET: WEEK 28 14/12/2015
DURATION TARGET: 5 WEEKS
I have altered my plan by adding a six week period beginning this week, for me to catch up with my sketchbook. I added the buffer weeks together and cut the construction phase by a week which allows me to comfortably restore past work. However, this put more pressure on me fulfilling the strict deadlines and although I will finish before the Christmas break, I may not finish before the 11/12/2015 which was the deadline set for our project. I have written an email stating this to my tutor explaining the situation and have asked for a week deadline extension.